Key points
- xAI installed eight converted jet engines in Mississippi for its Colossus 2 facility.
- Crusoe ordered 13 units for OpenAI's Abilene site and walked away from a Boom deal.
- Grid connection in Northern Virginia takes about seven years, while jet engines run in 24 months.
xAI has installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center, according to The New York Times report citing state permits and satellite imagery.reported This marks a shift toward self-generated power as grid connections remain slow.xAI is using old jet engines to power its data center because the electric grid is too slow.xAI deployed eight ProEnergy units in Mississippi to mitigate multi-year interconnection delays.
Evidence: reported
Data centers are turning to old jet engines as the wait for power growsaifleet-techcrunch
How we got here
Data center builders face years-long waits for grid access and new turbines. The International Energy Agency reports that hooking up 100 megawatts in Northern Virginia takes about seven years.reported Most new capacity is expected by 2031, a Mitsubishi Power executive told Bloomberg last week.reported
Evidence: reported
Data centers are turning to old jet engines as the wait for power growsaifleet-techcrunch
What is new
Companies are using rebuilt jet engines that burn natural gas. ProEnergy rebuilds GE engines from Boeing jets for this purpose. Crusoe, building OpenAI’s Stargate site in Abilene, Texas, ordered 13 such units in April 2025. xAI’s installation in Mississippi is confirmed via permits.
Reading between the lines
The Trump administration is encouraging data centers to generate their own electricity, adding pressure on builders. Microsoft withdrew as anchor customer for Nscale’s Loughton facility after the utility could not deliver power until the 2030s.reported Rystad Energy’s Audun Martinsen told The Times that speed is the main draw.
Evidence: reported
Data centers are turning to old jet engines as the wait for power growsaifleet-techcrunch
The open questions
The claim that jet engines solve power shortages must be weighed against their efficiency limits. Sources note these units are not permanent solutions. They are less environmentally friendly and less efficient than standard turbines. The evidence shows they buy time, not capacity.
Why it matters
- Model evaluators must account for variable power reliability when assessing facility uptime claims.
- Efficiency metrics for AI clusters may drop if powered by less efficient jet engines.
- Infrastructure delays could push deployment timelines beyond current estimates.
- Regulatory pressure for self-generation may reshape regional data center economics.
Topics: data centers, power infrastructure, AI hardware, energy policy
Updated
Then / now / next
Builders waited years for grid connections and standard turbines.
Companies install converted jet engines to power facilities in 24 months.
Watch for more self-generation projects as administration encourages it.
Story timeline
- Then Builders waited years for grid connections and standard turbines.
- 03 Nov 2026 Data centers are turning to old jet engines as the wait for power grows
- Now Companies install converted jet engines to power facilities in 24 months.
- Next Watch for more self-generation projects as administration encourages it.
The strongest doubt
Counterpoint from the sources
Converted jet engines are not permanent solutions and are less efficient than standard options.
Ask the article
Local keyword search of this article; no generated answers.Did this article give you the evidence you needed?
Your choice stays on this device. No public tally.Terms in this story
ProEnergy
Company that rebuilds GE jet engines for data center power.
Colossus 2
xAI data center facility located in Memphis, Mississippi.
Stargate
OpenAI data center site being built in Abilene, Texas.
Questions readers ask
Why use jet engines for data centers?
Grid connection waits are too long, taking up to seven years in some areas, while jet engines can be operational in 24 months.
Which companies are using this method?
xAI and Crusoe (for OpenAI) are using or ordering converted jet engines from ProEnergy.
Are these engines efficient?
No, sources describe them as less efficient and less environmentally friendly than permanent power plants.
Connected stories
Reading receipt
- xAI installed eight converted jet engines in Mississippi for its Colossus 2 facility.
- Crusoe ordered 13 units for OpenAI's Abilene site and walked away from a Boom deal.
- Grid connection in Northern Virginia takes about seven years, while jet engines run in 24 months.
Still open: How much efficiency is lost compared to standard gas turbines?
Still open: Will regulatory support for self-generation expand beyond current administration?